In the construction of the complex for the production of gasoline and aromatic hydrocarbons, the production line of the enterprise will be accomplished by the modern oil refining equipment and environmentally friendly technologies.
Thus, the advanced flare system will ensure complete combustion of emergency discharge of hydrocarbon gases in emergency situations and preparation of the equipment for scheduled repairs. Such facilities ensure complete and smoke-free combustion of the discharges coming to the torch with minimal thermal and light radiation significantly reducing the emissions of harmful substances into the atmosphere.
By July, the flare stack has been installed by 60%, the height of the erected metal structures is 30 meters. The assembly of the burner space inside the flare stack consisting of 75 highly efficient burners and a stage gas distribution system has already been completed. Air cooling units, drainage tanks, lighting masts, and instrument air separators have also been completed. The auxiliary equipment of the flare facility has been installed by 20%.
The technical re-equipment of industrial wastewater treatment facilities has been completed, as well as the construction of a new vertical stock tank RVS-5000.
In total, the modernization project will cover the construction of 30 production, energy and transport facilities, as well as combine unit LC-1500BK. The reconstruction will take place at all the industrial facilities. The equipment is contracted for 70%, construction and assembly works — for 85%, and design and survey work — for 100%.
A full range of engineering services for the design and construction is carried out by the specialists of KNGK-Group with more than 18 years of experience and successfully implemented projects in the sphere of construction of industrial facilities for oil and gas processing, storage of oil and petroleum products, gas supply, water supply and disposal, and transport.